Administration of Sponsored Projects (Monitoring Davis-Bacon Procedure)
The procedure for identifying and monitoring Davis-Bacon and
Connecticut Department of Labor prevailing wages and provisions related
to grant funded construction projects is as follows:
When a project request coded to grant funds (Ledger 5 or 6)
is received in Facilities Management, that office will notify
both Campus Planning and Purchasing.
Purchasing will review both the state and federal wage rates
related to Davis-Bacon to ensure that the proper rates are
published in the ensuing bid documents. Any variation in rates
(state to federal) would be addressed to the Standard Wage
Division of the Connecticut Department of Labor.
Once the contract is awarded, Campus Planning will contact
the contractor to coordinate the review of wages paid and the
installation of appropriate signage, at the job site, regarding
Davis-Bacon.
Campus Planning will review all contractor wage schedules and
payrolls and maintain those records. |